01 · An Fhadhb — The problem
Ireland is paying for clean power it doesn't use.
In 2024 the grid operator turned away 1,266 GWh of wind power in Ireland — 10.1% of the wind energy available — because the network could not take it. Some of those wind farms are compensated for the power they were not allowed to produce, and that cost is passed on to every electricity customer.
This site sets out the evidence, what it is likely to cost, and one option for using the surplus. Each figure shows its period, its source, and whether it is reported or modelled.
Wind power turned away
1,266 GWh
Ireland, 2024 — the latest year with a published EirGrid report
The same energy, mined at today’s network†
≈ €110M
≈ 1,500 BTC gross revenue, before costs. Whether it covers them is set out in step 03.
† Bitcoin figures · Modelled gross revenue at the BTC price (€75,800) and network hashrate on 4 October 2026 (stored snapshot — live data unavailable), before hardware, power and running costs. Not financial advice.
Year by year
Wind power turned away in Ireland, GWh
2025 (pale bar) is provisional: Volume (≈1,500 GWh) is Irish Grid’s estimate. Replace with the official report figure when it is published. 2020 was high because Covid-19 lockdowns cut demand.
Curtailment is not the same as constraint
Two kinds of dispatch-down
Both mean the grid operator telling a generator to produce less than it could. Curtailment is system-wide: there is more wind and solar than the whole island can safely run on at once. Constraint is local: the wires in one area cannot carry the power to where it is needed.
How it reaches bills
Generators with firm grid access are generally compensated when they are constrained; curtailment is largely unpaid for newer generators. When a constraint turns a wind farm down, other plant — often gas — is turned up elsewhere to keep supply and demand balanced. These costs are recovered through charges that suppliers pass on to customers.
What it is likely to cost
No public source gives the compensation paid for wind dispatch-down each year, so the cost here is modelled: the volume, split into constraint and curtailment, times assumed compensation rates, shown as a low–high range. The volume is reported; the cost is not. The assumptions are on the method page.
| Year | Wind turned away | Share of available wind | Compensation (modelled) | Per household | Volume basis |
|---|---|---|---|---|---|
| 2025 | ≈ 1,500 GWh | 11.3% | ≈ €72M€39M–€110M | ≈ €39€21–€58 | Provisional |
| 2024 | 1,266 GWh | 10.1% | ≈ €55M€28M–€84M | ≈ €30€15–€46 | EirGrid C&C report 2024 |
| 2023 | 1,124 GWh | 8.9% | ≈ €48M€17M–€81M | ≈ €26€9.40–€44 | EirGrid C&C report 2023 |
| 2022 | 988 GWh | 8.3% | ≈ €43M€15M–€71M | ≈ €23€8.30–€39 | EirGrid C&C report 2022 |
| 2021 | 752 GWh | 7.3% | ≈ €32M€12M–€54M | ≈ €18€6.30–€29 | EirGrid C&C report 2021 |
| 2020 | 1,448 GWh | 11.4% | ≈ €62M€22M–€100M | ≈ €34€12–€57 | EirGrid C&C report 2020 |
Volumes are wind only, Republic of Ireland, from EirGrid and SONI's annual Constraint and Curtailment reports; the latest year is provisional until its report is published. Every € figure is modelled: a central estimate with a low–high range, rounded to two significant figures. “Per household” divides the total by 1,841,152 private households (Census 2022) — it is an equivalent, not a line on any bill.
The assumptions behind the range
| Low | Central | High | |
|---|---|---|---|
| Compensation rate | €55/MWh | €75/MWh | €95/MWh |
| Constraint compensated | 80% | 95% | 100% |
| Curtailment compensated | 0% | 20% | 40% |
| Constraint share if not reported | 35% | 50% | 60% |
Context: replacing constrained power
When a constraint turns a wind farm down, the same power has to be bought from another generator. At a reference wholesale price of €95/MWh, the ≈ 633 GWh of constrained wind in 2024 is worth ≈ €60M. This is context, not an extra cost to add to the range above — and it excludes curtailment, where the power could not have been used at all.
Since 2021, a bigger share every year
Ireland aims for about 22 GW of wind and solar by 2030 under the Climate Action Plan — roughly three times what is connected today. Unless the grid, storage and demand keep pace, the share of clean power turned away grows with it.
2021
7.3%
2022
8.3%
2023
8.9%
2024
10.1%
2025 · provisional
≈ 11.3%
Why these differ · These are Ireland only. Across the whole island, including Northern Ireland, the share rose faster — 7.4% in 2021 to 14% in 2024. 2020 (11.4% in Ireland) is left out: Covid-19 lockdowns cut demand that year.
The uncomfortable maths
New wires, storage and interconnectors will help, but they take years to build. Until they arrive, adding wind to today's grid means turning away a bigger share of what is built, which weakens the case for the projects the climate targets depend on. The question is what to do with the surplus in the meantime, and who pays for it.
Lower bills, the climate targets and value for money all point the same way: use more of the clean power Ireland already produces.
Where the large generators are
EirGrid's reports put the highest dispatch-down in the west, north-west and south-west, where wind is strongest and the network is thinnest. The map shows a selection of large generators and interconnectors for orientation; it does not show output or dispatch-down by site, which EirGrid does not publish.
Next · 02 · An Líonra Bitcoin — The flexible load
What kind of electricity user could take this surplus when it appears, stop when homes need the power, and be sited where the wind is? One candidate is a network most people know only from the headlines.
The flexible load →