Skip to content
Irish Grid

01 · An Fhadhb — The problem

Ireland is paying for clean power it doesn't use.

In 2024 the grid operator turned away 1,266 GWh of wind power in Ireland — 10.1% of the wind energy available — because the network could not take it. Some of those wind farms are compensated for the power they were not allowed to produce, and that cost is passed on to every electricity customer.

This site sets out the evidence, what it is likely to cost, and one option for using the surplus. Each figure shows its period, its source, and whether it is reported or modelled.

Wind power turned away

1,266 GWh

Ireland, 2024 — the latest year with a published EirGrid report

Calendar 2024Ireland · windReported · EirGrid C&C report 2024

The same energy, mined at today’s network†

≈ €110M

≈ 1,500 BTC gross revenue, before costs. Whether it covers them is set out in step 03.

† €75,800 · 4 October 2026Modelled · gross, before costsStored snapshot

† Bitcoin figures · Modelled gross revenue at the BTC price (€75,800) and network hashrate on 4 October 2026 (stored snapshot — live data unavailable), before hardware, power and running costs. Not financial advice.

Year by year

Wind power turned away in Ireland, GWh

Calendar 2020–2025Ireland · windReported · EirGrid C&C reports

2025 (pale bar) is provisional: Volume (≈1,500 GWh) is Irish Grid’s estimate. Replace with the official report figure when it is published. 2020 was high because Covid-19 lockdowns cut demand.

Curtailment is not the same as constraint

Two kinds of dispatch-down

Both mean the grid operator telling a generator to produce less than it could. Curtailment is system-wide: there is more wind and solar than the whole island can safely run on at once. Constraint is local: the wires in one area cannot carry the power to where it is needed.

How it reaches bills

Generators with firm grid access are generally compensated when they are constrained; curtailment is largely unpaid for newer generators. When a constraint turns a wind farm down, other plant — often gas — is turned up elsewhere to keep supply and demand balanced. These costs are recovered through charges that suppliers pass on to customers.

What it is likely to cost

No public source gives the compensation paid for wind dispatch-down each year, so the cost here is modelled: the volume, split into constraint and curtailment, times assumed compensation rates, shown as a low–high range. The volume is reported; the cost is not. The assumptions are on the method page.

Wind dispatch-down in Ireland and its modelled cost, by year
YearWind turned awayShare of available windCompensation (modelled)Per householdVolume basis
2025≈ 1,500 GWh11.3%≈ €72M€39M–€110M≈ €39€21–€58Provisional
20241,266 GWh10.1%≈ €55M€28M–€84M≈ €30€15–€46EirGrid C&C report 2024
20231,124 GWh8.9%≈ €48M€17M–€81M≈ €26€9.40–€44EirGrid C&C report 2023
2022988 GWh8.3%≈ €43M€15M–€71M≈ €23€8.30–€39EirGrid C&C report 2022
2021752 GWh7.3%≈ €32M€12M–€54M≈ €18€6.30–€29EirGrid C&C report 2021
20201,448 GWh11.4%≈ €62M€22M–€100M≈ €34€12–€57EirGrid C&C report 2020

Volumes are wind only, Republic of Ireland, from EirGrid and SONI's annual Constraint and Curtailment reports; the latest year is provisional until its report is published. Every € figure is modelled: a central estimate with a low–high range, rounded to two significant figures. “Per household” divides the total by 1,841,152 private households (Census 2022) — it is an equivalent, not a line on any bill.

The assumptions behind the range
LowCentralHigh
Compensation rate€55/MWh€75/MWh€95/MWh
Constraint compensated80%95%100%
Curtailment compensated0%20%40%
Constraint share if not reported35%50%60%

Context: replacing constrained power

When a constraint turns a wind farm down, the same power has to be bought from another generator. At a reference wholesale price of €95/MWh, the ≈ 633 GWh of constrained wind in 2024 is worth ≈ €60M. This is context, not an extra cost to add to the range above — and it excludes curtailment, where the power could not have been used at all.

Calendar 2024Modelled

Since 2021, a bigger share every year

Ireland aims for about 22 GW of wind and solar by 2030 under the Climate Action Plan — roughly three times what is connected today. Unless the grid, storage and demand keep pace, the share of clean power turned away grows with it.

2021

7.3%

2022

8.3%

2023

8.9%

2024

10.1%

2025 · provisional

≈ 11.3%

Calendar 2021–2025Ireland · windShare of available wind · EirGrid C&C reports

Why these differ · These are Ireland only. Across the whole island, including Northern Ireland, the share rose faster — 7.4% in 2021 to 14% in 2024. 2020 (11.4% in Ireland) is left out: Covid-19 lockdowns cut demand that year.

The uncomfortable maths

New wires, storage and interconnectors will help, but they take years to build. Until they arrive, adding wind to today's grid means turning away a bigger share of what is built, which weakens the case for the projects the climate targets depend on. The question is what to do with the surplus in the meantime, and who pays for it.

Lower bills, the climate targets and value for money all point the same way: use more of the clean power Ireland already produces.

Where the large generators are

EirGrid's reports put the highest dispatch-down in the west, north-west and south-west, where wind is strongest and the network is thinnest. The map shows a selection of large generators and interconnectors for orientation; it does not show output or dispatch-down by site, which EirGrid does not publish.

Loading map…

Next · 02 · An Líonra Bitcoin — The flexible load

What kind of electricity user could take this surplus when it appears, stop when homes need the power, and be sited where the wind is? One candidate is a network most people know only from the headlines.

The flexible load →