Key figures
Wind power turned away in Ireland, 2024
1,266 GWh
EirGrid & SONI, Annual Renewable Energy Constraint and Curtailment Report 2024 (April 2025).
Share of available wind turned away
10.1%
Same report. Across the whole island the share was higher.
Compensation, modelled
≈ €55M
Range €28M–€84M; ≈ €30 per household. Not a published figure — please describe it as an Irish Grid estimate.
Gross mining revenue from that energy†
≈ €110M
Before costs, at today's price and network. Net of costs, under our central assumptions: ≈ -€58M.
Downloads
Embeddable widgets
Free to embed on any site or article. Copy the snippet:
Key figures
<iframe src="https://irishgrid.com/widget/cost" width="360" height="260" style="border:0" loading="lazy" title="Irish Grid — Key figures"></iframe>
Generator map
<iframe src="https://irishgrid.com/widget/map" width="440" height="640" style="border:0" loading="lazy" title="Irish Grid — Generator map"></iframe>
Mining calculator
<iframe src="https://irishgrid.com/widget/calculator" width="720" height="900" style="border:0" loading="lazy" title="Irish Grid — Mining calculator"></iframe>
Boilerplate
Irish Grid publishes independent evidence on Ireland's electricity grid: how much wind power is turned away, what it is likely to cost electricity customers, and options for using the surplus, including flexible demand. Reported figures come from EirGrid and SONI's annual Constraint and Curtailment reports; modelled figures are published with their assumptions. Irish Grid is an independent, non-partisan research and advocacy site. It has no connection to EirGrid or SONI.
Media contact: press@irishgrid.com